Processing Startup for Lead in China
The Shaoguan smelter reopened in February 2006 after waste‑treatment upgrades, restoring lead smelting capacity.
China production
Market intelligence
The Shaoguan smelter reopened in February 2006 after waste‑treatment upgrades, restoring lead smelting capacity.
Shenzhen Zhongjin Lingnan's Shaoguan smelter was forced to close in December 2005 after a toxic spill into the Beijing River.
Guangxi South Nonferrous Metal Smelting commenced a new electrolytic lead smelter in December 2005 with 80,000 t/yr capacity.
Yunnan Metallurgical began operations of a new lead‑zinc processing facility in December 2005, producing 100,000 t/yr each.
Panlong Lead and Zinc Mining Corp. commissioned its lead‑zinc mine in November 2005, with a 400 t/d ore processing capacity.
Zhishen Lead Industry started construction of a 100,000‑t/yr lead smelter in June 2005, targeting completion by end‑2006.
Xinhua Lead Industry commenced construction of a 60,000‑t/yr lead smelter in June 2005.
Xinling Lead Industry launched a 100,000‑t/yr lead smelter in May 2005.
Yuguang Gold & Lead Co. completed a 60,000‑t/yr refined lead upgrade in 2005, expanding capacity to 310,000 t/yr.
Eight lead smelters in Anhui province were demolished in 2005 for failing to meet environmental and licensing standards, reducing domestic lead smelting capacity.
Huludao Nonferrous Metals Group began building a new lead‑zinc smelter in 2005, slated to finish early 2006 with 30,000 t/yr lead capacity.
Chongqing Chunxing Alloys completed a 20,000‑t/yr secondary lead smelter in Chongqing in 2005.
Anyang Yubei Gold and Lead Co. finished a 50,000‑t/yr secondary lead smelter in Henan in 2005.
China's National Development and Reform Commission issued a 2005 industry guideline limiting new smelter construction below certain capacities, affecting future lead processing projects.