2017
Mine Restart for Indium in Belgium
Nyrstar restarted indium production at the Auby smelter in Q1 2017 after the fire‑induced shutdown.
Belgium production
Market intelligence
Nyrstar restarted indium production at the Auby smelter in Q1 2017 after the fire‑induced shutdown.
Nyrstar planned to increase Auby smelter capacity from 45 t/yr to 70 t/yr, with commissioning expected at the end of Q3 2016, expanding processing capacity.
A fire at Nyrstar’s Auby smelter in Belgium halted indium production in 2016, causing a temporary closure and delaying the restart.
Nyrstar’s Auby zinc smelter expanded indium recovery to 36.7 t in 2008, up from 15.8 t in 2007.